Optimização da Exploração de Recursos Hídricos considerando o Efeito de Queda
João Catalão
Sílvio Mariano
Victor Mendes
Luís Ferreira §
Departamento de Engenharia Electromecânica
UBI Universidade da Beira Interior
Departamento de Engenharia Electrotécnica e Automação
ISEL Instituto Superior de Engenharia de Lisboa
§ Departamento de Engenharia Electrotécnica e de Computadores
IST Instituto Superior Técnico
Title: Optimal scheduling of hydro power systems considering the head change effect.
Abstract
This paper focuses on the optimal scheduling of hydro power systems. A new methodology based on nonlinear optimisation is proposed for solving the problem considering the head change effect. The numerical results obtained for a case study illustrate the behaviour of the new methodology proposed.
Keywords: Optimal scheduling, Nonlinear optimisation, Head change effect
Resumo
Neste artigo é enunciado e descrito o problema de optimização da exploração de recursos hídricos. Uma nova metodologia baseada em optimização não linear é proposta para a resolução deste problema tendo em consideração o efeito de queda. Apresentam-se os resultados numéricos obtidos para um caso de estudo e conclui-se sobre o desempenho da nova metodologia proposta.
Texto completo apenas disponível em PDF.
Full text only in PDF.
6 Referências
Amado, S. M. and Ribeiro, C. C. (1987) Short-Term Generation Scheduling of Hydraulic Multi-Reservoir Multi-Area Interconnected Systems, IEEE Transactions on Power Systems, Vol. PWRS-2, No. 3, pp. 758-763. [ Links ]
Catalão, J. P. S., Mariano, S. J. P. S., Mendes, V. M. F., and Ferreira, L. A. F. M. (2006) Parameterisation Effect on the Behaviour of a Head-Dependent Hydro Chain using a Nonlinear Model, Electric Power Systems Research, Vol. 76, No. 6-7, pp. 404-412.
Catalão, J. P. S. (2006) Novas Metodologias de Optimização em Sistemas de Energia Hidrotérmicos, Dissertação de Doutoramento, Universidade da Beira Interior, Covilhã.
Cau, T. D. H. and Kaye, R. J. (2002) Evolutionary Optimisation Method for Multistorage Hydrothermal Scheduling, IEE Proceedings-Generation Transmission and Distribution, Vol. 149, No. 2, pp. 152-156.
Chang, G. W., Aganagic, M., Waight, J. G., Medina, J., Burton, T., Reeves, S., and Christoforidis, M. (2001) Experiences With Mixed Integer Linear Programming Based Approaches on Short-Term Hydro Scheduling, IEEE Transactions on Power Systems, Vol. 16, No. 4, pp. 743-749.
Chen, P. -H. and Chang, H. -C. (1996) Genetic Aided Scheduling of Hydraulically Coupled Plants in Hydro-Thermal Coordination, IEEE Transactions on Power Systems, Vol. 11, No. 2, pp. 975-981.
Conejo, A. J., Arroyo, J. M., Contreras, J., and Villamor, F. A. (2002) Self-Scheduling of a Hydro Producer in a Pool-Based Electricity Market, IEEE Transactions on Power Systems, Vol. 17, No. 4, pp. 1265-1272.
Ferreira, L. A. F. M., Anderson, T., Imparato, C. F., Miller, T. E., Pang, C. K., Svoboda, A., and Vojdani, A. F. (1989) Short-Term Resource Scheduling in Multi-Area Hydrothermal Power Systems, International Journal of Electrical Power & Energy Systems, Vol. 11, No. 3,
pp. 200-212.
Guan, X., Svoboda, A., and Li, C. -A. (1999) Scheduling Hydro Power Systems with Restricted Operating Zones and Discharge Ramping Constraints, IEEE Transactions on Power Systems, Vol. 14, No. 1, pp. 126-131.
Hreinsson, E. B. (1988) Optimal Short Term Operation of a Purely Hydroelectric System, IEEE Transactions on Power Systems, Vol. 3, No. 3, pp. 1072-1077.
Liang, R. -H. and Hsu, Y. -Y. (1996) Short-Term Hydro-Scheduling using Hopfield Neural Network, IEE Proceedings-Generation Transmission and Distribution, Vol. 143, No. 3, pp. 269-275.
Mariano, S. J. P. S., Catalão, J. P. S., Mendes, V. M. F., and Ferreira, L. A. F. M. (2006) Analysis of the Short-Term Profit-Based Behavior of a Hydroelectric Energy System using a Nonlinear Programming Method, Proceedings of the 19th Mini-EURO Conference on Operational Research Models and Methods in the Energy Sector, Coimbra, Portugal.
Naresh, R. and Sharma, J. (2002) Short Term Hydro Scheduling using Two-Phase Neural Network, International Journal of Electrical Power & Energy Systems, Vol. 24, No. 7, pp. 583-590.
Ni, E., Guan, X., and Li, R. (1999) Scheduling Hydrothermal Power Systems with Cascaded and Head-Dependent Reservoirs, IEEE Transactions on Power Systems, Vol. 14, No. 3, pp. 1127-1132.
Nilsson, O. and Sjelvgren, D. (1996) Mixed-Integer Programming Applied to Short-Term Planning of a Hydro-Thermal System, IEEE Transactions on Power Systems, Vol. 11, No. 1, pp. 281-286.
Piekutowski, M., Litwinowicz, T., and Frowd, R. J. (1994) Optimal Short-Term Scheduling for a Large-Scale Cascaded Hydro System, IEEE Transactions on Power Systems, Vol. 9, No. 2, pp. 805-811.
Pursimo, J. M., Antila, H. K., Vilkko, M. K., and Lautala, P. A. (1998) A Short-Term Scheduling for a Hydropower Power Plant, International Journal of Electrical Power & Energy Systems, Vol. 20, No. 8, pp. 525-532.
Wood, A. J. and Wollenberg, B. F. (1996) Power Generation, Operation and Control, Wiley, New York, USA.